| Assessment Year | 1996 |
|---|---|
| Principal Product | Breaded Meat Products |
| NAICS |
n/a
|
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
100,000
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $284,791 | 11,925,557 |
kWh
|
$0.024 |
| Electricity Demand | $205,596 | 2,466 |
kW-mo/yr
|
$83.37 |
| Electricity Fees | $42,642 | - |
|
- |
| Natural Gas | $137,803 | 50,896 |
MMBtu
|
$2.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $89,032 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $37,972 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $51,060 | - | - |
$51,060
-
kW-mo/yr
|
- | - | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,400 | - | - | - |
$6,400
-
MMBtu
|
- | |
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $1,740 | $5,400 |
$1,740
66,823
kWh
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $838 | $786 |
$487
18,757
kWh
|
$351
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $434 | $1,779 |
$287
11,137
kWh
|
$147
-
kW-mo/yr
|
- | - | |
| 06 | 3.6123: Burn wood by-products for heat | $28,560 | $29,500 | - |
$(-560.0)
-
kW-mo/yr
|
- |
$29,120
-
lb
|
|
| TOTAL RECOMMENDED | $89,032 | $37,465 |
$2,514
96,717
kWh
|
$50,998
-
kW-mo/yr
|
$6,400
-
MMBtu
|
$29,120
-
lb
|
||
| TOTAL IMPLEMENTED | $37,972 | $37,465 |
$2,514
96,717
kWh
|
$(-62.0)
-
kW-mo/yr
|
$6,400
-
MMBtu
|
$29,120
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs