ITAC Assessment: OK0479
ITAC logo
ITAC Assessment: OK0479
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Automotive rubber and weather stripping products
NAICS
n/a
SIC 2822: Synthetic Rubber (Vulcanizable Elastomers)
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 140,000
ft2
Annual Production 7,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $941,776 19,023,740
kWh
Natural Gas $50,583 16,668
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,493 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $53,983

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.7144: Install spectral reflectors / delamp $31,839 $70,726 $31,839
390,094
kWh
- -
02 2.7241: Install outside air damper / economizer on hvac unit $26,671 $25,000 $26,671
798,652
kWh
- -
03 2.4221: Install compressor air intakes in coolest locations $5,121 $2,948 $5,121
111,665
kWh
- -
04 2.7241: Install outside air damper / economizer on hvac unit $2,868 $3,950 $2,868
85,873
kWh
- -
05 2.7135: Install occupancy sensors $1,266 $528 $1,266
37,808
kWh
- -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $19,078 $11,000 $25,931
529,308
kWh
$(-6,853.0)
-
MMBtu
-
07 3.1192: Reduce scrap production $25,650 - - - $25,650
-
lb
TOTAL RECOMMENDED $112,493 $114,152 $93,696
1,953,400
kWh
$(-6,853.0)
-
MMBtu
$25,650
-
lb
TOTAL IMPLEMENTED $53,983 $18,426 $35,186
764,654
kWh
$(-6,853.0)
-
MMBtu
$25,650
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs