ITAC Assessment: OK0473
ITAC logo
ITAC Assessment: OK0473
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Feeds
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area 80,000
ft2
Annual Production 40,000
ton
Production Hrs. Annual 3,120
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $128,161 2,033,705
kWh
Natural Gas $52,901 11,041
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,394 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,336

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $17,879 - - - $17,879
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,058 $2,815 $2,058
46,014
kWh
- -
03 2.6232: Install set-back timers $1,006 $620 - $1,006
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $451 $40 $451
9,965
kWh
- -
TOTAL RECOMMENDED $21,394 $3,475 $2,509
55,979
kWh
$1,006
-
MMBtu
$17,879
TOTAL IMPLEMENTED $19,336 $660 $451
9,965
kWh
$1,006
-
MMBtu
$17,879
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs