Assessment Year | 1995 |
---|---|
Principal Product | Water source heat pumps |
NAICS |
n/a
|
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
286,000
ft2
|
Annual Production | 57,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $197,237 | 3,298,652 |
kWh
|
$0.060 |
Natural Gas | $49,819 | 15,972 |
MMBtu
|
$3.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,744 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $4,342 | $15,400 |
$4,342
123,388
kWh
|
- | - | |
02 | 2.4321: Upgrade obsolete equipment | $749 | $2,050 | - |
$749
-
MMBtu
|
- | |
03 | 2.7124: Make a practice of turning off lights when not needed | $817 | $200 |
$817
12,896
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $309 | $40 |
$309
9,965
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $225 | $224 |
$225
6,448
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $119 | $395 |
$119
2,345
kWh
|
- | - | |
07 | 3.8142: Distill contaminated solvents for reuse | $3,389 | $5,720 | - | - |
$3,389
-
gal
|
|
TOTAL RECOMMENDED | $9,950 | $24,029 |
$5,812
155,042
kWh
|
$749
-
MMBtu
|
$3,389
-
gal
|
||
TOTAL IMPLEMENTED | $5,744 | $18,109 |
$4,995
142,146
kWh
|
$749
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs