Assessment Year | 1993 |
---|---|
Principal Product | Residential Pressurized Water Tanks |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
126,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $144,397 | 2,866,940 |
kWh
|
$0.050 |
Natural Gas | $98,515 | 24,169 |
MMBtu
|
$4.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,336 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,331 | $180 |
$5,331
157,386
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,551 | - |
$3,551
70,047
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,614 | $5,045 |
$1,614
28,136
kWh
|
- | |
04 | 2.6232: Install set-back timers | $1,428 | $1,200 | - |
$1,428
-
MMBtu
|
|
05 | 2.4239: Eliminate or reduce compressed air usage | $922 | $790 |
$922
16,120
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $833 | $2,567 |
$833
9,379
kWh
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $827 | $946 |
$827
12,603
kWh
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $767 | - |
$767
14,068
kWh
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $447 | - |
$447
8,792
kWh
|
- | |
TOTAL RECOMMENDED | $15,720 | $10,728 |
$14,292
316,531
kWh
|
$1,428
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,336 | $8,161 |
$9,908
237,105
kWh
|
$1,428
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs