ITAC Assessment: OK0401
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Lenses, Semiconductor Material
NAICS
n/a
SIC 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum
Sales Range $10
M
to 50
M
# of Employees 107
Plant Area 36,095
ft2
Annual Production 24,000
pieces
Production Hrs. Annual 8,568
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,453 5,402,696
kWh
Natural Gas $39,163 10,472
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,955 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,098

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,436 $648 $2,436
67,116
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,229 $12,281 $7,229
143,611
kWh
-
03 2.6231: Utilize controls to operate equipment only when needed $1,081 $69 $1,081
42,497
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,239 $11,720 $4,239
140,973
kWh
-
05 2.2122: Install / repair insulation on condensate lines $352 $168 - $352
-
MMBtu
06 2.1121: Use insulation in furnaces to facilitate heating / cooling $21,033 $8,169 $21,033
824,736
kWh
-
07 2.2692: Use outside cold water source as a supply of cooling water $8,585 $31,250 $8,585
(-9,379)
kWh
-
TOTAL RECOMMENDED $44,955 $64,305 $44,603
1,209,554
kWh
$352
-
MMBtu
TOTAL IMPLEMENTED $11,098 $13,166 $10,746
253,224
kWh
$352
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs