| Assessment Year | 1993 |
|---|---|
| Principal Product | Livestock and Poultry Feeds |
| NAICS |
n/a
|
| SIC | 2875: Fertilizers, Mixing Only |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
93,500
ft2
|
| Annual Production | 120,000
ton
|
| Production Hrs. Annual | 7,476
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $232,458 | 4,892,145 |
kWh
|
$0.048 |
| Natural Gas | $54,292 | 18,466 |
MMBtu
|
$2.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,768 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,467 | $6,944 |
$2,467
22,274
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,326 | $6,750 |
$6,326
87,632
kWh
|
- | |
| 03 | 2.1241: Reduce excessive boiler blowdown | $865 | $1,270 | - |
$865
-
MMBtu
|
|
| 04 | 2.2122: Install / repair insulation on condensate lines | $110 | $296 | - |
$110
-
MMBtu
|
|
| 05 | 2.6232: Install set-back timers | $627 | $404 | - |
$627
-
MMBtu
|
|
| TOTAL RECOMMENDED | $10,395 | $15,664 |
$8,793
109,906
kWh
|
$1,602
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,768 | $15,260 |
$8,793
109,906
kWh
|
$975
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs