Assessment Year | 1993 |
---|---|
Principal Product | Livestock and Poultry Feeds |
NAICS |
n/a
|
SIC | 2875: Fertilizers, Mixing Only |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
93,500
ft2
|
Annual Production | 120,000
ton
|
Production Hrs. Annual | 7,476
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $232,458 | 4,892,145 |
kWh
|
$0.048 |
Natural Gas | $54,292 | 18,466 |
MMBtu
|
$2.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,768 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,467 | $6,944 |
$2,467
22,274
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,326 | $6,750 |
$6,326
87,632
kWh
|
- | |
03 | 2.1241: Reduce excessive boiler blowdown | $865 | $1,270 | - |
$865
-
MMBtu
|
|
04 | 2.2122: Install / repair insulation on condensate lines | $110 | $296 | - |
$110
-
MMBtu
|
|
05 | 2.6232: Install set-back timers | $627 | $404 | - |
$627
-
MMBtu
|
|
TOTAL RECOMMENDED | $10,395 | $15,664 |
$8,793
109,906
kWh
|
$1,602
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,768 | $15,260 |
$8,793
109,906
kWh
|
$975
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs