ITAC Assessment: OK0389
ITAC logo
ITAC Assessment: OK0389
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product STRUCTURAL STEEL
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area
n/a
Annual Production 65,000
ton
Production Hrs. Annual 6,864
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,834 966,589
kWh
Natural Gas $18,812 3,862
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,246 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,724

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,084 $200 $2,284
64,771
kWh
- $(-200.0)
02 2.7123: Keep lamps and reflectors clean $2,686 $6,210 $2,723
39,566
kWh
$(-280.0)
-
MMBtu
$243
03 2.7111: Reduce illumination to minimum necessary levels $1,437 $1,350 $1,437
28,722
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $941 $1,348 $576
8,499
kWh
- $365
05 2.7142: Utilize higher efficiency lamps and/or ballasts $262 $1,385 $469
3,810
kWh
$(-27.0)
-
MMBtu
$(-180.0)
06 2.7261: Install timers and/or thermostats $371 $203 - $371
-
MMBtu
-
07 2.4221: Install compressor air intakes in coolest locations $201 $683 $201
5,569
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $264 $147 $264
2,345
kWh
- -
TOTAL RECOMMENDED $8,246 $11,526 $7,954
153,282
kWh
$64
-
MMBtu
$228
TOTAL IMPLEMENTED $4,724 $4,283 $4,766
105,802
kWh
$(-27.0)
-
MMBtu
$(-15.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs