Assessment Year | 1992 |
---|---|
Principal Product | COMMERCIAL PRINTING |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,799 | 3,435,229 |
kWh
|
$0.044 |
Natural Gas | $38,592 | 13,809 |
MMBtu
|
$2.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,660 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,113 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $2,316 | $1,715 |
$2,316
-
kWh
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,094 | $376 |
$1,094
29,601
kWh
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $453 | $1,203 | - |
$453
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,797 | - |
$2,150
35,756
kWh
|
- | $(-353.0) | |
TOTAL RECOMMENDED | $5,660 | $3,294 |
$5,560
65,357
kWh
|
$453
-
MMBtu
|
$(-353.0) | ||
TOTAL IMPLEMENTED | $4,113 | $1,715 |
$4,466
35,756
kWh
|
- | $(-353.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs