Assessment Year | 2000 |
---|---|
Principal Product | Gourmet Specialty Foods |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
55,000
ft2
|
Annual Production | 9,000,000
lb
|
Production Hrs. Annual | 4,789
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $133,540 | 1,643,980 |
kWh
|
$0.081 |
Electricity Demand | $17,137 | 4,174 |
kW-mo/yr
|
$4.11 |
Natural Gas | $35,452 | 5,649 |
MMBtu
|
$6.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,011 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $67,953 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $1,188 | - |
$1,188
14,634
kWh
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $2,105 | - |
$2,105
22,987
kWh
|
- | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $2,740 | - |
$2,740
33,746
kWh
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $1,090 | $296 |
$1,090
10,718
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $6,043 | $1,750 |
$6,043
70,437
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,970 | $1,123 |
$2,970
34,603
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,968 | $29,300 |
$12,968
143,380
kWh
|
- | - | |
08 | 3.5217: Reuse / recycle/ sell paper products | $4,565 | - | - |
$4,565
-
lb
|
- | |
09 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $6,079 | - | - |
$6,079
-
lb
|
- | |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $42,263 | $32,184 | - | - | $42,263 | |
TOTAL RECOMMENDED | $82,011 | $64,653 |
$29,104
330,505
kWh
|
$10,644
-
lb
|
$42,263 | ||
TOTAL IMPLEMENTED | $67,953 | $35,057 |
$15,046
176,407
kWh
|
$10,644
-
lb
|
$42,263 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs