| Assessment Year | 1991 |
|---|---|
| Principal Product | INGOTS AND ANODES |
| NAICS |
n/a
|
| SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
n/a
|
| Annual Production | 125,000,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $333,646 | 6,796,893 |
kWh
|
$0.049 |
| Natural Gas | $546,710 | 272,092 |
MMBtu
|
$2.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,804 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $70,804 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $534 | - |
$511
14,947
kWh
|
- | $23 | |
| 02 | 2.7261: Install timers and/or thermostats | $254 | $360 |
$109
3,224
kWh
|
$145
-
MMBtu
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $60,081 | $58,228 |
$60,081
1,751,172
kWh
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,311 | - |
$1,311
31,653
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,377 | - |
$1,467
42,790
kWh
|
- | $(-90.0) | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,152 | - |
$4,152
99,941
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,095 | - |
$3,236
80,305
kWh
|
- | $(-141.0) | |
| TOTAL RECOMMENDED | $70,804 | $58,588 |
$70,867
2,024,032
kWh
|
$145
-
MMBtu
|
$(-208.0) | ||
| TOTAL IMPLEMENTED | $70,804 | $58,588 |
$70,867
2,024,032
kWh
|
$145
-
MMBtu
|
$(-208.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs