ITAC Assessment: OK0353
ITAC logo
ITAC Assessment: OK0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PASSENGER BELT SYSTEMS
NAICS
n/a
SIC 3535: Conveyors and Conveying Equipment
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area
n/a
Annual Production 60
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,549 291,911
kWh
Natural Gas $5,916 1,423
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,050 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $3,147 $1,050 - $3,147
-
MMBtu
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $234 - $234
2,931
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $379 - $429
9,965
kWh
- $(-50.0)
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $200 - $200
2,345
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $88 $120 $88
1,172
kWh
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,002 $5,000 $1,002
22,860
kWh
- -
TOTAL RECOMMENDED $5,050 $6,170 $1,953
39,273
kWh
$3,147
-
MMBtu
$(-50.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs