Assessment Year | 1991 |
---|---|
Principal Product | POWDERED METAL PARTS |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
n/a
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $157,443 | 2,912,954 |
kWh
|
$0.054 |
Natural Gas | $17,220 | 2,565 |
MMBtu
|
$6.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,475 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3511: Use plant owned transformers or lease transformers | $10,327 | $13,900 |
$10,327
-
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $15,053 | - |
$40,294
881,887
kWh
|
$(-25,241.0)
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,637 | - |
$1,737
53,341
kWh
|
- | $(-100.0) | |
04 | 2.7261: Install timers and/or thermostats | $458 | $750 | - |
$458
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $27,475 | $14,650 |
$52,358
935,228
kWh
|
$(-24,783.0)
-
MMBtu
|
$(-100.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs