ITAC Assessment: OK0349
ITAC logo
ITAC Assessment: OK0349
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PLEASURE BOATS
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area
n/a
Annual Production 500
pieces
Production Hrs. Annual 2,032
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $56,233 1,182,005
kWh
Natural Gas $20,419 4,730
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,580 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $10,208 $1,900 - $10,208
-
MMBtu
-
02 2.2437: Recover waste heat from equipment $1,603 $1,860 - $1,603
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $310 - $360
7,913
kWh
- $(-50.0)
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $168 - $168
3,810
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $291 $900 $291
6,448
kWh
- -
TOTAL RECOMMENDED $12,580 $4,660 $819
18,171
kWh
$11,811
-
MMBtu
$(-50.0)
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs