ITAC Assessment: OK0309
ITAC logo
ITAC Assessment: OK0309
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product TREATED POSTS
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $5
M
to 10
M
# of Employees 53
Plant Area
n/a
Annual Production 52,000
ton
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,566 221,864
kWh
LPG $34,020 7,420
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,599 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,968

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Wood Savings Administrative Changes Savings
01 3.6123: Burn wood by-products for heat $12,631 $17,000 - $34,020
-
MMBtu
$(-3,889.0)
-
MMBtu
$(-17,500.0)
02 2.4221: Install compressor air intakes in coolest locations $114 $221 $114
879
kWh
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $357 - $357
2,638
kWh
- - -
04 2.4312: Improve lubrication practices $1,235 - $1,235
9,379
kWh
- - -
05 2.4133: Use most efficient type of electric motors $262 $579 $262
2,052
kWh
- - -
TOTAL RECOMMENDED $14,599 $17,800 $1,968
14,948
kWh
$34,020
-
MMBtu
$(-3,889.0)
-
MMBtu
$(-17,500.0)
TOTAL IMPLEMENTED $1,968 $800 $1,968
14,948
kWh
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs