| Assessment Year | 1990 |
|---|---|
| Principal Product | CAM & GROOVE COUPLINGS |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
n/a
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $241,437 | 3,849,062 |
kWh
|
$0.063 |
| Natural Gas | $63,633 | 23,158 |
MMBtu
|
$2.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,413 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,969 | $27,903 |
$14,969
309,203
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $859 | $640 |
$859
18,464
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $110 | $102 |
$110
1,465
kWh
|
- | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $18,384 | - |
$41,472
-
kWh
|
- | $(-23,088.0) | |
| 05 | 2.3212: Optimize plant power factor | $10,716 | $16,250 |
$10,716
-
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $810 | $1,300 |
$810
17,585
kWh
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,419 | - |
$1,719
48,652
kWh
|
- | $(-300.0) | |
| 08 | 2.7261: Install timers and/or thermostats | $493 | $150 | - |
$493
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $47,760 | $46,345 |
$70,655
395,369
kWh
|
$493
-
MMBtu
|
$(-23,388.0) | ||
| TOTAL IMPLEMENTED | $1,413 | $1,552 |
$920
19,050
kWh
|
$493
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs