ITAC Assessment: OK0302
ITAC logo
ITAC Assessment: OK0302
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product MOLDED RUBBER PRODUCTS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 120
Plant Area
n/a
Annual Production 51,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $71,268 1,507,034
kWh
Natural Gas $5,265 1,207
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,012 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $991

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $484 $167 $484
10,551
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $491 $640 $242
4,103
kWh
- $249
03 2.4133: Use most efficient type of electric motors $134 $280 $134
2,931
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $310 $487 $417
8,499
kWh
- $(-107.0)
05 2.7261: Install timers and/or thermostats $373 $630 - $373
-
MMBtu
-
06 2.2511: Insulate bare equipment $265 $120 $265
9,086
kWh
- -
07 2.3212: Optimize plant power factor $955 $2,600 $955
17,585
kWh
- -
TOTAL RECOMMENDED $3,012 $4,924 $2,497
52,755
kWh
$373
-
MMBtu
$142
TOTAL IMPLEMENTED $991 $1,077 $618
13,482
kWh
$373
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs