Assessment Year | 2020 |
---|---|
Principal Product | Architectural coatings |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
28,927
ft2
|
Annual Production | 335
Tgal
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,966 | 189,760 |
kWh
|
$0.14 |
Electricity Demand | $24,794 | 981 |
kW-mo/yr
|
$25.27 |
Electricity Fees | $216 | - |
|
- |
Fuel Oil #2 | $15,855 | 875 |
MMBtu
|
$18.12 |
TOTAL YEARLY COSTS | $66,831 | |||
RECOMMENDED SAVINGS* | $36,222 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $927 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $30,760 | $129,192 |
$21,992
160,528
kWh
|
- | $8,768 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,862 | $11,220 |
$1,472
10,745
kWh
|
$1,390
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,673 | $7,900 |
$864
6,306
kWh
|
$809
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $723 | $300 |
$723
5,281
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $204 | $200 |
$204
1,487
kWh
|
- | - | |
TOTAL RECOMMENDED | $36,222 | $148,812 |
$25,255
184,347
kWh
|
$2,199
-
kW-mo/yr
|
$8,768 | ||
TOTAL IMPLEMENTED | $927 | $500 |
$927
6,768
kWh
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs