ITAC Assessment: OK0299
ITAC logo
ITAC Assessment: OK0299
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product FABRICATED AIRCRAFT PARTS
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 96
Plant Area
n/a
Annual Production 1,270
pieces
Production Hrs. Annual 2,574
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,991 907,093
kWh
Natural Gas $10,100 2,195
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,669 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,451

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6241: Reduce temperature of process equipment when on standby $7,885 $23,283 $7,885
116,940
kWh
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $1,218 $823 - $1,218
-
MMBtu
03 2.4133: Use most efficient type of electric motors $566 $783 $566
5,569
kWh
-
TOTAL RECOMMENDED $9,669 $24,889 $8,451
122,509
kWh
$1,218
-
MMBtu
TOTAL IMPLEMENTED $8,451 $24,066 $8,451
122,509
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs