ITAC Assessment: OK0284
ITAC logo
ITAC Assessment: OK0284
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product FABRICATED STEEL
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 260
Plant Area
n/a
Annual Production 400,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $164,893 3,378,077
kWh
Natural Gas $28,986 9,765
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $56,255 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $56,255

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $738 $1,250 - $738
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $34,480 $36,560 $34,462
703,107
kWh
- $18
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,250 $3,808 $1,366
27,843
kWh
- $(-116.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $400 $825 $400
6,741
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $289 $275 $289
4,982
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $560 $3,432 $632
15,826
kWh
- $(-72.0)
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,197 $31,028 $10,197
318,581
kWh
- -
08 2.2437: Recover waste heat from equipment $6,816 $2,140 - $6,816
-
MMBtu
-
09 2.3513: Consider power loss as well as initial loads and load growth in down-sizing transformers $1,525 - $1,745
54,513
kWh
- $(-220.0)
TOTAL RECOMMENDED $56,255 $79,318 $49,091
1,131,593
kWh
$7,554
-
MMBtu
$(-390.0)
TOTAL IMPLEMENTED $56,255 $79,318 $49,091
1,131,593
kWh
$7,554
-
MMBtu
$(-390.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs