| Assessment Year | 1989 |
|---|---|
| Principal Product | ALIMINUM BEVERAGE CANS |
| NAICS |
n/a
|
| SIC | 3411: Metal Cans |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
n/a
|
| Annual Production | 27,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $491,113 | 11,626,905 |
kWh
|
$0.042 |
| Natural Gas | $154,634 | 46,472 |
MMBtu
|
$3.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $71,139 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,850 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $24,830 | $4,924 | - |
$24,830
-
MMBtu
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,286 | - |
$8,586
238,570
kWh
|
- | $(-300.0) | |
| 03 | 2.4133: Use most efficient type of electric motors | $1,433 | $1,256 |
$1,433
33,411
kWh
|
- | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $3,508 | $475 |
$3,200
73,564
kWh
|
- | $308 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,030 | $255 |
$1,030
22,860
kWh
|
- | - | |
| 06 | 2.7261: Install timers and/or thermostats | $264 | $84 | - |
$264
-
MMBtu
|
- | |
| 07 | 2.3212: Optimize plant power factor | $2,541 | $3,000 |
$2,541
-
kWh
|
- | - | |
| 08 | 2.3511: Use plant owned transformers or lease transformers | $27,517 | $67,000 |
$27,517
-
kWh
|
- | - | |
| 09 | 2.2444: Use hot process fluids to preheat incoming process fluids | $1,730 | $390 | - |
$1,730
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $71,139 | $77,384 |
$44,307
368,405
kWh
|
$26,824
-
MMBtu
|
$8 | ||
| TOTAL IMPLEMENTED | $39,850 | $9,825 |
$13,590
294,841
kWh
|
$26,560
-
MMBtu
|
$(-300.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs