ITAC Assessment: OK0279
ITAC logo
ITAC Assessment: OK0279
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product POULTRY BY-PRODUCT MEAL
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $10
M
to 50
M
# of Employees 19
Plant Area
n/a
Annual Production 2,000
ton
Production Hrs. Annual 6,864
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,482 4,400,059
kWh
Natural Gas $505,785 185,075
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $115,000 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,049

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,397 $3,483 $1,704
48,066
kWh
- $(-307.0)
02 2.6232: Install set-back timers $506 $400 $506
11,430
kWh
- -
03 2.2511: Insulate bare equipment $2,236 $2,512 - $2,236
-
MMBtu
-
04 2.2511: Insulate bare equipment $5,203 $2,516 - $5,203
-
MMBtu
-
05 2.2136: Install / repair insulation on steam lines $15,708 $10,392 - $15,708
-
MMBtu
-
06 2.1233: Analyze flue gas for proper air/fuel ratio $15,332 $1,500 - $15,332
-
MMBtu
-
07 2.2135: Repair and eliminate steam leaks $22,796 - - $22,796
-
MMBtu
-
08 2.3511: Use plant owned transformers or lease transformers $18,520 $38,000 $18,520
-
kWh
- -
09 2.4133: Use most efficient type of electric motors $697 $513 $697
18,464
kWh
- -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,992 - $1,992
52,755
kWh
- -
11 3.4151: Minimize water usage $15,726 $4,050 - $14,144
-
MMBtu
$1,582
12 2.2414: Use waste heat from hot flue gases to preheat $14,887 $7,200 - $14,887
-
MMBtu
-
TOTAL RECOMMENDED $115,000 $70,566 $23,419
130,715
kWh
$90,306
-
MMBtu
$1,275
TOTAL IMPLEMENTED $57,049 $6,463 $3,195
82,649
kWh
$52,272
-
MMBtu
$1,582
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs