ITAC Assessment: OK0253
ITAC logo
ITAC Assessment: OK0253
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product HEAT EXCHANGERS
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 52
Plant Area
n/a
Annual Production 400
pieces
Production Hrs. Annual 2,350
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,686 740,035
kWh
Natural Gas $22,074 5,470
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,725 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,098

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $5,363 $1,200 - $5,363
-
MMBtu
-
02 2.4322: Use or replace with energy efficient substitutes $1,357 - $694
11,723
kWh
- $663
03 2.7142: Utilize higher efficiency lamps and/or ballasts $225 $57 $225
3,810
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $83 $159 $83
1,465
kWh
- -
05 2.7231: Use radiant heater for spot heating $4,721 $13,000 - $4,721
-
MMBtu
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,613 - $2,753
46,600
kWh
- $(-140.0)
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,319 - $1,319
22,274
kWh
- -
08 2.4133: Use most efficient type of electric motors $44 $88 $44
879
kWh
- -
TOTAL RECOMMENDED $15,725 $14,504 $5,118
86,751
kWh
$10,084
-
MMBtu
$523
TOTAL IMPLEMENTED $14,098 $14,288 $3,491
59,202
kWh
$10,084
-
MMBtu
$523
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs