ITAC Assessment: OK0244
ITAC logo
ITAC Assessment: OK0244
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product PIPE FITTINGS
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area
n/a
Annual Production 84,246
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,289 696,073
kWh
Natural Gas $12,362 3,009
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,562 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,673

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $301 $159 $301
4,689
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $122 $255 $122
1,758
kWh
- -
03 2.2437: Recover waste heat from equipment $302 $420 - $302
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $435 - $545
14,947
kWh
- $(-110.0)
05 2.7261: Install timers and/or thermostats $1,766 $1,040 - $1,766
-
MMBtu
-
06 2.6232: Install set-back timers $415 $115 $415
6,155
kWh
- -
07 2.7111: Reduce illumination to minimum necessary levels $172 $20 $172
2,638
kWh
- -
08 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $717 $380 $717
10,551
kWh
- -
09 2.4239: Eliminate or reduce compressed air usage $332 $275 $332
9,086
kWh
- -
TOTAL RECOMMENDED $4,562 $2,664 $2,604
49,824
kWh
$2,068
-
MMBtu
$(-110.0)
TOTAL IMPLEMENTED $3,673 $2,264 $1,715
36,635
kWh
$2,068
-
MMBtu
$(-110.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs