| Assessment Year | 1988 |
|---|---|
| Principal Product | STEEL FABRICATION |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $5 M to 10M |
| # of Employees | 75 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $74,803 | 1,080,891 |
kWh
|
$0.069 |
| Natural Gas | $79,272 | 22,522 |
MMBtu
|
$3.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,605 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,487 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,869 | $7,200 |
$2,518
36,342
kWh
|
- | $351 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,185 | - |
$2,325
33,705
kWh
|
- | $(-140.0) | |
| 03 | 2.7261: Install timers and/or thermostats | $101 | $150 | - |
$101
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $249 | $294 | - |
$249
-
MMBtu
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $133 | $227 |
$133
2,052
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $68 | - |
$68
1,172
kWh
|
- | - | |
| TOTAL RECOMMENDED | $5,605 | $7,871 |
$5,044
73,271
kWh
|
$350
-
MMBtu
|
$211 | ||
| TOTAL IMPLEMENTED | $2,487 | $377 |
$2,526
36,929
kWh
|
$101
-
MMBtu
|
$(-140.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs