ITAC Assessment: OK0242
ITAC logo
ITAC Assessment: OK0242
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product IODINE
NAICS
n/a
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 27
Plant Area
n/a
Annual Production 2,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,941,191 44,481,536
kWh
Natural Gas $76,461 63,718
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $560,769 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,747

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $557,022 $852,179 $771,100
17,379,836
kWh
$(-166,078.0)
-
MMBtu
$(-48,000.0)
02 2.6232: Install set-back timers $3,249 $400 $3,249
55,979
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $498 $209 $498
8,792
kWh
- -
TOTAL RECOMMENDED $560,769 $852,788 $774,847
17,444,607
kWh
$(-166,078.0)
-
MMBtu
$(-48,000.0)
TOTAL IMPLEMENTED $3,747 $609 $3,747
64,771
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs