Assessment Year | 1987 |
---|---|
Principal Product | STEEL CASTINGS |
NAICS |
n/a
|
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 94 |
Plant Area |
n/a
|
Annual Production | 1,500
ton
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $219,892 | 5,021,102 |
kWh
|
$0.044 |
Natural Gas | $141,985 | 33,087 |
MMBtu
|
$4.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $263 | $105 |
$263
4,103
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $964 | - |
$1,334
39,566
kWh
|
- | $(-370.0) | |
03 | 2.7261: Install timers and/or thermostats | $17,160 | $1,500 | - |
$17,160
-
MMBtu
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,068 | $2,500 | - |
$6,068
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,923 | $28,665 |
$8,923
143,025
kWh
|
- | - | |
06 | 2.2515: Use optimum thickness insulation | $1,643 | $6,000 | - |
$1,643
-
MMBtu
|
- | |
07 | 2.2437: Recover waste heat from equipment | $3,369 | $1,219 | - |
$3,369
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $38,390 | $39,989 |
$10,520
186,694
kWh
|
$28,240
-
MMBtu
|
$(-370.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs