Assessment Year | 2016 |
---|---|
Principal Product | Fabricated structural steel |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
140,433
ft2
|
Annual Production | 175,000
pieces
|
Production Hrs. Annual | 2,392
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,859 | 1,557,396 |
kWh
|
$0.038 |
Electricity Demand | $126,454 | 7,062 |
kW-mo/yr
|
$17.91 |
Electricity Fees | $4,659 | - |
|
- |
Natural Gas | $45,663 | 7,655 |
MMBtu
|
$5.97 |
TOTAL YEARLY COSTS | $235,635 | |||
RECOMMENDED SAVINGS* | $22,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,340 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,340 | $1,500 |
$1,340
39,400
kWh
|
$2,000
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,680 | $57,330 |
$4,600
133,300
kWh
|
$10,370
-
kW-mo/yr
|
$150 | $560 | |
03 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $3,080 | $13,230 |
$590
16,700
kWh
|
$2,490
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $22,100 | $72,060 |
$6,530
189,400
kWh
|
$14,860
-
kW-mo/yr
|
$150 | $560 | ||
TOTAL IMPLEMENTED | $3,340 | $1,500 |
$1,340
39,400
kWh
|
$2,000
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs