| Assessment Year | 1987 |
|---|---|
| Principal Product | SWITCHES & GAUGES |
| NAICS |
n/a
|
| SIC | 3613: Switchgear and Switchboard Apparatus |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 180,000
pieces
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,877 | 691,970 |
kWh
|
$0.068 |
| Natural Gas | $10,071 | 2,024 |
MMBtu
|
$4.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,328 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,328 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $759 | $238 |
$822
13,189
kWh
|
$(-63.0)
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $353 | $734 |
$382
5,862
kWh
|
$(-29.0)
-
MMBtu
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $241 | $80 |
$241
5,862
kWh
|
- | - | |
| 04 | 2.7261: Install timers and/or thermostats | $2,644 | $3,300 | - |
$2,644
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $283 | - |
$343
11,137
kWh
|
- | $(-60.0) | |
| 06 | 2.8112: Combine utility meters | $768 | $520 | - |
$768
-
MMBtu
|
- | |
| 07 | 2.3191: Use demand controller or load shedder | $1,280 | $820 |
$1,280
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $6,328 | $5,692 |
$3,068
36,050
kWh
|
$3,320
-
MMBtu
|
$(-60.0) | ||
| TOTAL IMPLEMENTED | $6,328 | $5,692 |
$3,068
36,050
kWh
|
$3,320
-
MMBtu
|
$(-60.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs