ITAC Assessment: OK0230
ITAC logo
ITAC Assessment: OK0230
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product STEEL CASTING
NAICS
n/a
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area
n/a
Annual Production 3,600,000
pieces
Production Hrs. Annual 0
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $228,680 4,387,163
kWh
Natural Gas $82,745 21,321
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,681 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,907

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $999 - $999
28,136
kWh
-
02 2.2511: Insulate bare equipment $669 $1,450 - $669
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $105 $154 $105
2,052
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $331 $55 $331
9,379
kWh
-
05 2.4322: Use or replace with energy efficient substitutes $23,577 $4,125 - $23,577
-
MMBtu
TOTAL RECOMMENDED $25,681 $5,784 $1,435
39,567
kWh
$24,246
-
MMBtu
TOTAL IMPLEMENTED $24,907 $4,180 $1,330
37,515
kWh
$23,577
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs