ITAC Assessment: OK0224
ITAC logo
ITAC Assessment: OK0224
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product STEEL FABRICATION
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $5
M
to 10
M
# of Employees 64
Plant Area
n/a
Annual Production 3,500,000
lb
Production Hrs. Annual 2,850
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,511 504,103
kWh
Natural Gas $12,211 3,742
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,328 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,328

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $610 $185 $668
13,189
kWh
$(-58.0)
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $333 $547 $333
3,517
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,012 $2,117 $1,072
11,137
kWh
$(-60.0)
-
MMBtu
04 2.7261: Install timers and/or thermostats $6,373 $456 $1,154
16,999
kWh
$5,219
-
MMBtu
TOTAL RECOMMENDED $8,328 $3,305 $3,227
44,842
kWh
$5,101
-
MMBtu
TOTAL IMPLEMENTED $8,328 $3,305 $3,227
44,842
kWh
$5,101
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs