Assessment Year | 1987 |
---|---|
Principal Product | COMBUSTION BURNERS |
NAICS |
n/a
|
SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
n/a
|
Annual Production | 4,000
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,872 | 1,196,366 |
kWh
|
$0.054 |
Natural Gas | $52,782 | 13,913 |
MMBtu
|
$3.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,347 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,298 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $8,049 | $1,300 |
$(-3,776.0)
(-59,789)
kWh
|
$11,825
-
MMBtu
|
- | |
02 | 2.7261: Install timers and/or thermostats | $4,180 | $2,250 | - |
$4,180
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $753 | - |
$813
16,413
kWh
|
- | $(-60.0) | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $97 | $60 |
$97
1,465
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,363 | $5,742 |
$3,757
102,579
kWh
|
$(-394.0)
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,905 | - |
$3,182
73,271
kWh
|
$(-277.0)
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $19,347 | $9,352 |
$4,073
133,939
kWh
|
$15,334
-
MMBtu
|
$(-60.0) | ||
TOTAL IMPLEMENTED | $11,298 | $8,052 |
$7,849
193,728
kWh
|
$3,509
-
MMBtu
|
$(-60.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs