ITAC Assessment: SD0496
ITAC logo
ITAC Assessment: SD0496
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Corrugated paper boxes
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range less than $500
k
# of Employees 150
Plant Area 175,000
ft2
Annual Production 80,001
units
Production Hrs. Annual 7,488
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,276 1,096,327
kWh
Electricity Demand $62,893 2,673
kW-mo/yr
Electricity Fees $6,290 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,365 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $66,819

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7232: Replace existing hvac unit with high efficiency model $43,186 $113,400 $18,259
252,533
kWh
$24,927
-
kW-mo/yr
02 2.7135: Install occupancy sensors $10,851 $12,449 $10,851
150,081
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $9,239 $7,006 $6,072
83,965
kWh
$3,167
-
kW-mo/yr
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,546 $18,500 - $5,546
-
kW-mo/yr
05 2.7134: Use photocell controls $2,674 $2,420 $2,120
29,319
kWh
$554
-
kW-mo/yr
06 2.7132: Install timers on light switches in little used areas $869 $1,356 $695
9,608
kWh
$174
-
kW-mo/yr
TOTAL RECOMMENDED $72,365 $155,131 $37,997
525,506
kWh
$34,368
-
kW-mo/yr
TOTAL IMPLEMENTED $66,819 $136,631 $37,997
525,506
kWh
$28,822
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs