ITAC Assessment: OK0212
ITAC logo
ITAC Assessment: OK0212
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product STEEL UTILITY POLES
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,420
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,541 2,153,869
kWh
Natural Gas $52,483 13,632
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,946 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,946

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2437: Recover waste heat from equipment $1,745 $485 - $1,745
-
MMBtu
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,403 - $4,843
109,027
kWh
- $(-440.0)
03 2.7261: Install timers and/or thermostats $378 $450 - $378
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,372 $212 $1,372
28,136
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $11,167 $1,575 $11,167
157,386
kWh
- -
06 2.6232: Install set-back timers $1,748 - $1,748
29,015
kWh
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,133 - $3,702
-
kWh
- $(-569.0)
TOTAL RECOMMENDED $23,946 $2,722 $22,832
323,564
kWh
$2,123
-
MMBtu
$(-1,009.0)
TOTAL IMPLEMENTED $23,946 $2,722 $22,832
323,564
kWh
$2,123
-
MMBtu
$(-1,009.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs