ITAC Assessment: OK0198
ITAC logo
ITAC Assessment: OK0198
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product OPTHALMIC MACHINERY
NAICS
n/a
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 380
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $183,961 3,728,312
kWh
Natural Gas $32,131 7,736
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,578 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,883

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2514: Cover open tanks $1,722 $426 - $1,722
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $340 $60 $340
7,034
kWh
-
03 2.4133: Use most efficient type of electric motors $101 $49 $101
2,345
kWh
-
04 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $5,532 $22,000 $5,532
104,631
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $8,027 $276 $9,339
240,035
kWh
$(-1,312.0)
-
MMBtu
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,856 $3,272 $3,925
82,063
kWh
$(-69.0)
-
MMBtu
TOTAL RECOMMENDED $19,578 $26,083 $19,237
436,108
kWh
$341
-
MMBtu
TOTAL IMPLEMENTED $11,883 $3,548 $13,264
322,098
kWh
$(-1,381.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs