Assessment Year | 1986 |
---|---|
Principal Product | OILS & GREASES (BLENDING) |
NAICS |
n/a
|
SIC | 2992: Lubricating Oils and Greases |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 168,000
bbl
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,361 | 2,413,540 |
kWh
|
$0.061 |
Natural Gas | $252,609 | 65,545 |
MMBtu
|
$3.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,861 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,281 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,573 | $2,082 |
$4,573
68,288
kWh
|
- | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $3,617 | - | - |
$3,617
-
MMBtu
|
|
03 | 2.7261: Install timers and/or thermostats | $4,105 | $5,300 | - |
$4,105
-
MMBtu
|
|
04 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $16,774 | $35,620 |
$20,499
318,288
kWh
|
$(-3,725.0)
-
MMBtu
|
|
05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,672 | $21,000 | - |
$5,672
-
MMBtu
|
|
06 | 2.2124: Install de-aerator in place of condensate tank | $6,444 | $30,000 | - |
$6,444
-
MMBtu
|
|
07 | 2.2122: Install / repair insulation on condensate lines | $986 | $2,550 | - |
$986
-
MMBtu
|
|
08 | 2.2514: Cover open tanks | $2,690 | $533 | - |
$2,690
-
MMBtu
|
|
TOTAL RECOMMENDED | $44,861 | $97,085 |
$25,072
386,576
kWh
|
$19,789
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,281 | $9,932 |
$4,573
68,288
kWh
|
$8,708
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs