Assessment Year | 1985 |
---|---|
Principal Product | HEAT EXCHANGERS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
n/a
|
Annual Production | 300
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,471 | 1,072,098 |
kWh
|
$0.051 |
Natural Gas | $30,658 | 8,161 |
MMBtu
|
$3.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,672 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,376 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $1,296 | $3,847 |
$1,296
-
kWh
|
- | |
02 | 2.7261: Install timers and/or thermostats | $271 | $600 | - |
$271
-
MMBtu
|
|
03 | 2.7231: Use radiant heater for spot heating | $12,890 | $4,700 | - |
$12,890
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $215 | $248 |
$215
5,275
kWh
|
- | |
TOTAL RECOMMENDED | $14,672 | $9,395 |
$1,511
5,275
kWh
|
$13,161
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,376 | $5,548 |
$215
5,275
kWh
|
$13,161
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs