ITAC Assessment: OK0158
ITAC logo
ITAC Assessment: OK0158
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product GASKET & BOLT SETS
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $1
M
to 5
M
# of Employees 27
Plant Area
n/a
Annual Production 12,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $9,025 133,939
kWh
Natural Gas $4,130 852
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,062

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7111: Reduce illumination to minimum necessary levels $60 - $60
879
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $161 $33 $161
2,345
kWh
-
03 2.7261: Install timers and/or thermostats $93 $100 - $93
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $638 $180 $638
9,672
kWh
-
05 2.7231: Use radiant heater for spot heating $1,375 $76 $34
586
kWh
$1,341
-
MMBtu
06 2.6212: Turn off equipment during breaks, reduce operating time $1,828 $3,400 $1,749
26,084
kWh
$79
-
MMBtu
TOTAL RECOMMENDED $4,155 $3,789 $2,642
39,566
kWh
$1,513
-
MMBtu
TOTAL IMPLEMENTED $4,062 $3,689 $2,642
39,566
kWh
$1,420
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs