Assessment Year | 2012 |
---|---|
Principal Product | Doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
210,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 4,600
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $253,557 | 6,051,939 |
kWh
|
$0.042 |
Electricity Demand | $149,567 | 14,830 |
kW-mo/yr
|
$10.09 |
Electricity Fees | $2,051 | - |
|
- |
Natural Gas | $124,775 | 12,670 |
MMBtu
|
$9.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $194,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $56,541 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $21,080 | $25,000 |
$12,847
308,824
kWh
|
$8,233
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.1336: Install equipment to utilize waste fuel | $107,890 | $305,000 | - | - |
$112,890
-
MMBtu
|
- | - | $(-5,000.0) | |
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $8,910 | $20,000 | - | - |
$8,910
-
MMBtu
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,190 | $400 |
$4,283
102,948
kWh
|
$2,747
-
kW-mo/yr
|
- | $(-600.0) | - | $(-240.0) | |
05 | 2.4239: Eliminate or reduce compressed air usage | $102 | $200 |
$62
1,491
kWh
|
$40
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2437: Recover waste heat from equipment | $7,686 | $11,000 |
$(-143.0)
(-3,435)
kWh
|
$(-91.0)
-
kW-mo/yr
|
$7,920
-
MMBtu
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,392 | $8,400 |
$22,492
534,262
kWh
|
$14,244
-
kW-mo/yr
|
- | - | $(-344.0) | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,997 | $18,991 |
$3,601
85,524
kWh
|
$2,396
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $174 | $220 |
$56
1,327
kWh
|
$78
-
kW-mo/yr
|
- | - | - | $40 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $528 | $508 |
$157
3,718
kWh
|
$52
-
kW-mo/yr
|
- | - | - | $319 | |
TOTAL RECOMMENDED | $194,949 | $389,719 |
$43,355
1,034,659
kWh
|
$27,699
-
kW-mo/yr
|
$129,720
-
MMBtu
|
$(-600.0) | $(-344.0) | $(-4,881.0) | ||
TOTAL IMPLEMENTED | $56,541 | $39,211 |
$30,351
722,117
kWh
|
$19,414
-
kW-mo/yr
|
$7,920
-
MMBtu
|
$(-600.0) | $(-344.0) | $(-200.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs