Assessment Year | 1999 |
---|---|
Principal Product | cable assemblies and sheet metal |
NAICS |
n/a
|
SIC | 3670: |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
106,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $94,136 | 1,412,661 |
kWh
|
$0.067 |
Electricity Demand | $26,544 | 3,546 |
kW-mo/yr
|
$7.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,025 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,213 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,757 | $13,042 |
$3,726
55,979
kWh
|
$1,031
-
kW-mo/yr
|
- | |
02 | 2.7144: Install spectral reflectors / delamp | $1,812 | $3,000 |
$1,296
19,343
kWh
|
$516
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,087 | - |
$759
11,430
kWh
|
$328
-
kW-mo/yr
|
- | |
04 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $704 | $400 |
$518
7,913
kWh
|
$186
-
kW-mo/yr
|
- | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $3,845 | $240 |
$3,163
47,479
kWh
|
$682
-
kW-mo/yr
|
- | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,820 | - | - | - | $11,820 | |
TOTAL RECOMMENDED | $24,025 | $16,682 |
$9,462
142,144
kWh
|
$2,743
-
kW-mo/yr
|
$11,820 | ||
TOTAL IMPLEMENTED | $22,213 | $13,682 |
$8,166
122,801
kWh
|
$2,227
-
kW-mo/yr
|
$11,820 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs