Assessment Year | 1986 |
---|---|
Principal Product | CORRUGATED BOARDS,CONTAINERS |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 56 |
Plant Area |
n/a
|
Annual Production | 310,000
thousand feet
|
Production Hrs. Annual | 4,320
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $77,679 | 1,038,980 |
kWh
|
$0.075 |
Fuel Oil #6 | $75,625 | 17,678 |
MMBtu
|
$4.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,155 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,773 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $482 | $300 |
$482
6,448
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,147 | - |
$2,147
28,722
kWh
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $565 | $1,136 | - |
$565
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,271 | $119 |
$1,271
16,999
kWh
|
- | |
05 | 2.4312: Improve lubrication practices | $1,753 | $300 |
$1,753
23,447
kWh
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $789 | $800 |
$789
10,551
kWh
|
- | |
07 | 2.2437: Recover waste heat from equipment | $1,134 | $1,075 |
$(-22.0)
(-293)
kWh
|
$1,156
-
MMBtu
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,014 | $7,500 |
$2,914
38,980
kWh
|
$100
-
MMBtu
|
|
TOTAL RECOMMENDED | $11,155 | $11,230 |
$9,334
124,854
kWh
|
$1,821
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,773 | $10,630 |
$4,952
66,237
kWh
|
$1,821
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs