ITAC Assessment: OK0156
ITAC logo
ITAC Assessment: OK0156
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product AUTO PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area
n/a
Annual Production 50,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $441,337 10,800,117
kWh
Natural Gas $214,869 43,663
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,658 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,034

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $567 $161 $567
11,723
kWh
- -
02 2.3212: Optimize plant power factor $5,639 $7,640 $5,639
-
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $16,728 $14,629 $15,524
394,490
kWh
- $1,204
04 3.4115: Recover and reuse cooling water $1,387 $500 $29
586
kWh
- $1,358
05 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,307 $624 $2,307
50,996
kWh
- -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $9,735 - $11,400
-
kWh
- $(-1,665.0)
07 2.6212: Turn off equipment during breaks, reduce operating time $1,633 $531 $575
17,585
kWh
$1,058
-
MMBtu
-
08 2.2511: Insulate bare equipment $300 $329 - $300
-
MMBtu
-
09 2.7261: Install timers and/or thermostats $1,230 $300 - $1,230
-
MMBtu
-
10 2.7221: Lower temperature during the winter season and vice-versa $2,411 - - $2,411
-
MMBtu
-
11 2.2511: Insulate bare equipment $290 $880 - $290
-
MMBtu
-
12 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $11,431 - $3,800
116,354
kWh
$7,631
-
MMBtu
-
TOTAL RECOMMENDED $53,658 $25,594 $39,841
591,734
kWh
$12,920
-
MMBtu
$897
TOTAL IMPLEMENTED $12,034 $9,644 $7,975
51,582
kWh
$2,701
-
MMBtu
$1,358
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs