| Assessment Year | 1985 |
|---|---|
| Principal Product | AUTO PARTS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 225 |
| Plant Area |
n/a
|
| Annual Production | 50,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $441,337 | 10,800,117 |
kWh
|
$0.041 |
| Natural Gas | $214,869 | 43,663 |
MMBtu
|
$4.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $53,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,034 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $567 | $161 |
$567
11,723
kWh
|
- | - | |
| 02 | 2.3212: Optimize plant power factor | $5,639 | $7,640 |
$5,639
-
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,728 | $14,629 |
$15,524
394,490
kWh
|
- | $1,204 | |
| 04 | 3.4115: Recover and reuse cooling water | $1,387 | $500 |
$29
586
kWh
|
- | $1,358 | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,307 | $624 |
$2,307
50,996
kWh
|
- | - | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,735 | - |
$11,400
-
kWh
|
- | $(-1,665.0) | |
| 07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,633 | $531 |
$575
17,585
kWh
|
$1,058
-
MMBtu
|
- | |
| 08 | 2.2511: Insulate bare equipment | $300 | $329 | - |
$300
-
MMBtu
|
- | |
| 09 | 2.7261: Install timers and/or thermostats | $1,230 | $300 | - |
$1,230
-
MMBtu
|
- | |
| 10 | 2.7221: Lower temperature during the winter season and vice-versa | $2,411 | - | - |
$2,411
-
MMBtu
|
- | |
| 11 | 2.2511: Insulate bare equipment | $290 | $880 | - |
$290
-
MMBtu
|
- | |
| 12 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $11,431 | - |
$3,800
116,354
kWh
|
$7,631
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $53,658 | $25,594 |
$39,841
591,734
kWh
|
$12,920
-
MMBtu
|
$897 | ||
| TOTAL IMPLEMENTED | $12,034 | $9,644 |
$7,975
51,582
kWh
|
$2,701
-
MMBtu
|
$1,358 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs