Assessment Year | 1984 |
---|---|
Principal Product | CHROMIUM PLATING |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,188 | 839,977 |
kWh
|
$0.043 |
Natural Gas | $29,980 | 6,748 |
MMBtu
|
$4.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,436 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $542 | $500 | - |
$542
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $596 | $334 |
$596
12,309
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $318 | $810 |
$183
3,517
kWh
|
- | $135 | |
04 | 2.2511: Insulate bare equipment | $589 | $291 | - |
$589
-
MMBtu
|
- | |
05 | 2.2514: Cover open tanks | $2,628 | $555 | - |
$2,628
-
MMBtu
|
- | |
06 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $5,709 | $16,000 |
$(-605.0)
(-15,826)
kWh
|
$6,314
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $10,382 | $18,490 |
$174
-
kWh
|
$10,073
-
MMBtu
|
$135 | ||
TOTAL IMPLEMENTED | $7,436 | $17,125 |
$(-9.0)
(-3,517)
kWh
|
$7,445
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs