Assessment Year | 1984 |
---|---|
Principal Product | RECYCLED FERROUS METALS |
NAICS |
n/a
|
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,450
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $82,460 | 1,308,031 |
kWh
|
$0.063 |
Natural Gas | $64,733 | 17,624 |
MMBtu
|
$3.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,058 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $595 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,469 | $450 | - |
$3,559
-
MMBtu
|
$(-90.0) | |
02 | 2.2511: Insulate bare equipment | $1,714 | $580 | - |
$1,714
-
MMBtu
|
- | |
03 | 2.7261: Install timers and/or thermostats | $200 | $400 | - |
$200
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $280 | - |
$220
3,517
kWh
|
- | $60 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $212 | $427 |
$161
2,638
kWh
|
- | $51 | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $93 | - |
$93
1,465
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $90 | $30 |
$90
1,465
kWh
|
- | - | |
TOTAL RECOMMENDED | $6,058 | $1,887 |
$564
9,085
kWh
|
$5,473
-
MMBtu
|
$21 | ||
TOTAL IMPLEMENTED | $595 | $857 |
$344
5,568
kWh
|
$200
-
MMBtu
|
$51 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs