Assessment Year | 1984 |
---|---|
Principal Product | PRINTED CIRCUIT BOARDS |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
n/a
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 3,175
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $44,861 | 825,909 |
kWh
|
$0.054 |
Natural Gas | $3,017 | 663 |
MMBtu
|
$4.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,192 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,909 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,133 | $856 |
$1,133
24,326
kWh
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $190 | $226 |
$190
4,103
kWh
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $207 | $198 | - |
$207
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $338 | $596 |
$219
5,862
kWh
|
- | $119 | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $505 | $344 | - |
$505
-
MMBtu
|
- | |
06 | 2.7226: Use computer programs to optimize hvac performance | $588 | $1,228 |
$588
19,930
kWh
|
- | - | |
07 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $40 | $50 |
$40
1,465
kWh
|
- | - | |
08 | 2.7229: Air condition only space necessary | $191 | $440 | - |
$191
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $3,192 | $3,938 |
$2,170
55,686
kWh
|
$903
-
MMBtu
|
$119 | ||
TOTAL IMPLEMENTED | $1,909 | $2,140 |
$1,392
31,653
kWh
|
$398
-
MMBtu
|
$119 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs