| Assessment Year | 1984 |
|---|---|
| Principal Product | HEAT EXCHANGER DESIGN |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $1 M to 5M |
| # of Employees | 31 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $11,971 | 195,780 |
kWh
|
$0.061 |
| Natural Gas | $1,768 | 389 |
MMBtu
|
$4.54 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $2,113 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,455 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $344 | $434 |
$344
5,569
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $744 | - | - |
$744
-
MMBtu
|
|
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $658 | - |
$658
10,844
kWh
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $367 | - |
$367
6,155
kWh
|
- | |
| TOTAL RECOMMENDED | $2,113 | $434 |
$1,369
22,568
kWh
|
$744
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,455 | $434 |
$711
11,724
kWh
|
$744
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs