| Assessment Year | 1984 |
|---|---|
| Principal Product | PUMPS & VALVES |
| NAICS |
n/a
|
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 280 |
| Plant Area |
n/a
|
| Annual Production | 9,000
pieces
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,253 | 2,644,490 |
kWh
|
$0.050 |
| Natural Gas | $58,216 | 16,386 |
MMBtu
|
$3.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,833 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,833 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $1,155 | $535 | - |
$1,155
-
MMBtu
|
|
| 02 | 2.2437: Recover waste heat from equipment | $153 | $211 | - |
$153
-
MMBtu
|
|
| 03 | 2.7314: Reduce ventilation air | $1,502 | $12 |
$124
4,103
kWh
|
$1,378
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $253 | $365 | - |
$253
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,231 | $1,913 |
$1,231
24,619
kWh
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,416 | $704 |
$1,416
37,222
kWh
|
- | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $123 | $36 |
$123
2,345
kWh
|
- | |
| TOTAL RECOMMENDED | $5,833 | $3,776 |
$2,894
68,289
kWh
|
$2,939
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,833 | $3,776 |
$2,894
68,289
kWh
|
$2,939
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs