| Assessment Year | 1983 |
|---|---|
| Principal Product | GRAINS/ANIMAL FOOD |
| NAICS |
n/a
|
| SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
| Sales Range | $5 M to 10M |
| # of Employees | 64 |
| Plant Area |
n/a
|
| Annual Production | 4,000,000
lb
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $221,405 | 5,604,924 |
kWh
|
$0.040 |
| Natural Gas | $200,459 | 60,968 |
MMBtu
|
$3.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,481 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $52 | $57 |
$52
1,172
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $162 | $600 | - |
$162
-
MMBtu
|
|
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,042 | $800 | - |
$10,042
-
MMBtu
|
|
| 04 | 2.2511: Insulate bare equipment | $4,220 | $1,029 | - |
$4,220
-
MMBtu
|
|
| 05 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $1,686 | $1,000 | - |
$1,686
-
MMBtu
|
|
| 06 | 2.6218: Turn off equipment when not in use | $212 | $700 |
$212
7,034
kWh
|
- | |
| 07 | 2.2135: Repair and eliminate steam leaks | $6,954 | $2,350 | - |
$6,954
-
MMBtu
|
|
| 08 | 2.4133: Use most efficient type of electric motors | $2,932 | $5,105 |
$2,932
62,720
kWh
|
- | |
| 09 | 2.3212: Optimize plant power factor | $3,221 | $4,137 |
$3,221
-
kWh
|
- | |
| TOTAL RECOMMENDED | $29,481 | $15,778 |
$6,417
70,926
kWh
|
$23,064
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs