ITAC Assessment: OK0093
ITAC logo
ITAC Assessment: OK0093
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product GRAY IRON FOUNDRIES
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $10
M
to 50
M
# of Employees 41
Plant Area
n/a
Annual Production 10,000,000
lb
Production Hrs. Annual 1,800
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $350,497 7,915,592
kWh
Natural Gas $93,780 29,958
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,455 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $470 $824 - $470
-
MMBtu
02 2.4133: Use most efficient type of electric motors $752 $2,405 $752
27,257
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $233 $103 $233
4,396
kWh
-
TOTAL RECOMMENDED $1,455 $3,332 $985
31,653
kWh
$470
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs