ITAC Assessment: OK0090
ITAC logo
ITAC Assessment: OK0090
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product PIZZA TOPPINGS
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area
n/a
Annual Production 2,808,000
lb
Production Hrs. Annual 2,100
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,398 597,011
kWh
Natural Gas $7,119 1,939
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,816 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,606

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $210 $340 - $210
-
MMBtu
02 2.3212: Optimize plant power factor $1,104 $1,103 $1,104
-
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $1,010 $695 - $1,010
-
MMBtu
04 2.2136: Install / repair insulation on steam lines $141 $196 - $141
-
MMBtu
05 3.1192: Reduce scrap production $1,351 $5,000 - $1,351
-
MMBtu
TOTAL RECOMMENDED $3,816 $7,334 $1,104
-
kWh
$2,712
-
MMBtu
TOTAL IMPLEMENTED $3,606 $6,994 $1,104
-
kWh
$2,502
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs